The 27.5 MWp ground-mounted PV station was installed on a former military base in the Lower Spreewald in Brandenburg. The station was completed and commissioned in August 2012.
- 27.5 MWp ground-mounted PV station
- EPC, O&M, and financing by Enerparc
- 14-week construction period
- Completed in August 2012